Terracing for a new railroad between the terminal and the inland track. The work includes shaft, filling, ducting, unloading and crushing.
2017-2019
Execution contract
HS-Magasin
Construction of deposition pond for highly sulfuric material. Includes shaft and fill of 1,700,000m³ of material.
2018-2019
Turnkey contract
PT33 Vaikijaur
Shafts, filling, concrete, ducting, maneuvering, fences for 130kV and 40kV switchgear.
2018-2019
Execution contract
Bridge over GC road
Construction of bypass for Riksväg 45 before the start of the bridge construction. Shaft of ground and rocks. Concrete works for a new bridge, refilling and reconstruction of the road. New railings and refuges on the road section affected by the construction. New walkway and cycle path under the new bridge and connection to existing roads on both sides of the E45.
2018
Execution contract
Drainage actions
Drainage of railway area. Installation and adjustment of tracks. Shafts, filling, electrical and insulation work in soil. Laying of cylinders.
2014
General contract
HYTTSOTSDEPONI POND CONSTRUCTION
Shaft and fill and sealing layer for deposit 8
2014 - 2015
Turnkey contract
Block Termiten
Ground work on new construction of mobile housing for the elderly at Block Termiten, Kiruna.
2015
General contract
The Likskär embankment
Demolition, sealing of road bank and support filling and erosion protection. Shaft and structure of new road superstructure and new opto-channel
2015
General contract
M3 plant work new blast furnace
Ground and construction work in connection with the construction of new blast furnace 3
2015
General contract
Linbäcks site
Shafts, fill and water works